LQPF15 · Marion, Texas · 80 acres (32,37 ha · 323 700 m²)

Parque residencial de viviendas prefabricadas y vehículos recreativos · LQ INVESTMENTS PORTFOLIO FIFTEEN LLC

Home
LandQuire desk

El terrenoSatellite · LandID · Google Maps · Photos — and the progress at a glance

3D terrain
Click two points to measure · layers top right
✓ Propiedad LandQuire
LQ INVESTMENTS PORTFOLIO FIFTEEN LLC
✓ Propiedad LandQuire
LQ INVESTMENTS PORTFOLIO FIFTEEN LLC
Satellite + boundaries · parcel in yellow · measure the distance to sewer, road or schoolEsri, Maxar, USDA · OpenStreetMap

80 acres (32,37 ha · 323 700 m²) of raw land · Marion, Texas · 542 lots projected · Parque residencial de viviendas prefabricadas y vehículos recreativos

Project progressInstaGantt · 20/09/2026
90 %Overall project progressrefreshed every 3 h
18Total tasks14Completed4Remaining
100 %Topografíarefreshed every 3 h
3Total tasks3Completed0Remaining
100 %Planes e informesrefreshed every 3 h
7Total tasks7Completed0Remaining
87 %Condado de Guadaluperefreshed every 3 h
5Total tasks2Completed3Remaining
Current milestonePlanteamiento generalEst. timeframe: septiembre de 2026Milestone progress75 %

Progress, task counts and target dates come from the team’s InstaGantt export, picked up automatically every 3 hours. Dates are planning targets, not commitments.

Q4 2027 – Q4 2028Disposition — resale windowPrepared in parallel · projected net result 2 150 945 $*
100 %Funded & acquiredCapitalización del proyecto 2 324 865 $ · Land acquired on 29/10/2025

* Projected figures from the pro forma (original projection) — neither a promise nor a guarantee of performance. Progress and milestones: InstaGantt export of 20/09/2026. Capitalization and disposition: LQWealth registry of 2026-09-18.

Where it standsFunded · value-add underway · disposition prepared in parallel

Project phase
Land acquired 29/10/2025 · last permit target diciembre de 2026 · resale window Q4 2027 – Q4 2028
Value-add — entitlement 90 % complete

In the value-add phase, the 4 markers track the land acquisition and regulatory progress.

Team notes — 4 markers
Team weekly note · 03/09/2026
Acquisition documentsConfirmed

Yes — seller contract on file: "Executed PSA - Stagecoach"

FuenteDocs (data room) · LandQuire team update · 28/04/2026
Progreso de las autorizacionesEn progreso

Due diligence in progress — plans submitted and under review, fees to be paid for comments to be released

FuenteDeclarado por Willem · en curso · LandQuire team update · 02/07/2026
Adquisición del terrenoConfirmed

Land acquired on 29/10/2025.

FuenteDeducido de la etapa (registro) · LandQuire team update · 18/09/2026
Actividad recienteConfirmed

Estacionamiento junto al pad en lugar de en el derecho de paso

FuenteDeclarado por Willem · confirmado · LandQuire team update · 03/09/2026
Key dates
On file, then the schedule
Land acquired
Registro LQWealth
29/10/2025
Last permit target
Registro de plano · InstaGantt
diciembre de 2026
Resale window
Hold period on the LQWealth registry
Q4 2027 – Q4 2028
LQPF15 · Under Mgmt · LQ INVESTMENTS PORTFOLIO FIFTEEN LLC

Topografía 100 % · Planes e informes 100 % · Condado de Guadalupe 87 %.

Entitlement tracking · 22 permit lines · 16 completeExport 20/09/2026

Latest weekly note · 03/09/2026

Estacionamiento junto al pad en lugar de en el derecho de paso
Se obtendrían más lotes para viviendas móviles de una sección en lugar de viviendas móviles de doble sección
Si las viviendas tienen entradas laterales, las escaleras contarán como la distancia desde la otra vivienda
El condado está satisfecho con el diseño del componente RV del parque
La planta de tratamiento de aguas residuales es bien recibida como plan para evitar tener que dividir en múltiples lotes
Up next — from the project schedule
Condado de Guadalupe
septiembre de 2026Planteamiento general
octubre de 2026Permiso de entrada
diciembre de 2026Aprobación de TCEQ para el permiso de WWTF
Unphased
diciembre de 2026Registro de plano
2 324 865 $Capital invested
10 %Preferred return
64 %Projected investor ROI *
21 %Projected investor IRR *

* Pro forma, original projection — LQWealth registry. Neither a promise nor a guarantee of performance.

The latest plan — Site planSee the plans
A question about this deal?
The LandQuire team answers you directly on this page.
Hacer una pregunta

Entitlement updatePermit tracking · InstaGantt · weekly notes

Permit tracking — all 22 lines
90 % complete
Current reviewPlanteamiento general75 % · target septiembre de 2026
Lines2216 complete · 6 upcoming
Next targetsseptiembre de 2026 · octubre de 2026 · diciembre de 2026
Permit tracking — line by line, on the calendar
Hover a bar for start, duration and target
Task · start · duration%
mayjunjulagosepoctnovdicenefebmarabrmayjunjulagosepoctnovdic
Target
Parque MH Stagecoachmayo de 2025 · 1 año 7 meses 14 días
90 %
diciembre de 2026
Topografíamayo de 2025 · 2 meses 1 día
100 %
julio de 2025
Límitemayo de 2025 · 2 meses 1 día
100 %
julio de 2025
Topográficomayo de 2025 · 2 meses 1 día
100 %
julio de 2025
Árbolmayo de 2025 · 2 meses 1 día
100 %
julio de 2025
Plan conceptualjunio de 2025 · 15 días
100 %
junio de 2025
Reunión del condadojulio de 2025 · 3 días
100 %
julio de 2025
Planes e informesjulio de 2025 · 7 meses 4 días
100 %
enero de 2026
Planes de desarrollo del sitiojulio de 2025 · 7 meses 4 días
100 %
enero de 2026
Análisis de impacto de tráficojulio de 2025 · 7 meses 4 días
100 %
enero de 2026
Planes de manejo de aguas pluvialesjulio de 2025 · 4 meses 24 días
100 %
noviembre de 2025
Planes de Mejora de la Red de Agua Públicajulio de 2025 · 4 meses 22 días
100 %
noviembre de 2025
Diseño y Planes de Estanque de Detenciónagosto de 2025 · 2 meses 25 días
100 %
octubre de 2025
Plan de mitigación de árbolesjulio de 2025 · 3 meses 1 día
100 %
septiembre de 2025
SWPPPjulio de 2025 · 2 meses 28 días
100 %
septiembre de 2025
Condado de Guadalupenoviembre de 2025 · 1 año 1 mes 28 días
87 %
diciembre de 2026
Planteamiento generalnoviembre de 2025 · 10 meses 27 días
75 %
septiembre de 2026
Tráficonoviembre de 2025 · 9 meses 29 días
100 %
agosto de 2026
Aprobación de TCEQ para el permiso de WWTFnoviembre de 2025 · 1 año 1 mes 28 días
80 %
diciembre de 2026
Drenaje de tormentanoviembre de 2025 · 9 meses 29 días
100 %
agosto de 2026
Permiso de entradanoviembre de 2025 · 1 año 2 días
85 %
octubre de 2026
Registro de planomarzo de 2026 · 9 meses 6 días
70 %
diciembre de 2026

export 2026-09-20 · InstaGantt

Update history — team weekly notes
03/09/2026
  • Estacionamiento junto al pad en lugar de en el derecho de paso
  • Se obtendrían más lotes para viviendas móviles de una sección en lugar de viviendas móviles de doble sección
  • Si las viviendas tienen entradas laterales, las escaleras contarán como la distancia desde la otra vivienda
  • El condado está satisfecho con el diseño del componente RV del parque
  • La planta de tratamiento de aguas residuales es bien recibida como plan para evitar tener que dividir en múltiples lotes
11/08/2026
  • Contacto de seguimiento tras su confirmación de que recibieron todos los documentos necesarios para nuestra solicitud
  • Carta de autorización para firmar y enviar a Wilson
31/07/2026
  • Recibimos las tarifas de adquisición de agua de GVSUD que se adeudarían a la aprobación de los planos, para formar parte del loan de construcción
  • Esperamos un paquete de formularios que necesitan en 2 semanas para dar seguimiento a nuestra presentación
See full history (+32)
28/07/2026
  • Nuestros planos están en revisión por el condado
  • Recibimos comentarios positivos sobre nuestros planos para una WWTF en lugar de OSSF para el proyecto
23/07/2026
  • Los planos están presentados y en revisión durante los próximos 30 días (¡fecha límite importante a finales de agosto!)
  • Pago de tasas pendiente para que se emitan los comentarios
  • Se apunta a dos rondas de presentación para obtener las aprobaciones
15/07/2026
  • Planos de construcción a presentar esta semana para revisión
  • El TIA fue pagado por nuestra parte, tarifas de revisión del condado que serían aplicables
  • Plazo de revisión aún por determinar
07/07/2026
  • Finalizando el informe de drenaje esta semana, a presentar a comienzos de la próxima semana
  • Asegurarse de que se realizó el pago del TIA
  • Plazo de revisión aún por determinar
01/07/2026
  • El TIA debe presentarse al condado, se recibirá factura para pago
  • Presentación al condado para realizar esta semana
23/06/2026
  • Los planos se presentarán a finales de la semana (informe de drenaje a revisar previamente)
  • Contactar a la compañía eléctrica para el diseño (líneas trifásicas en la carretera)
  • Presentar el lunes o martes al condado (plazo de revisión por determinar)
16/06/2026
  • El movimiento de tierras está terminado y se está redimensionando el plan general para reducir el material de relleno necesario para el proyecto
  • Planes para presentar la próxima semana
02/06/2026
  • Los planos están en revisión y se presentarán al condado antes del viernes
  • Finalizando el diseño
28/05/2026
  • Los planos se están actualizando; se enviarán al condado la próxima semana (periodo de revisión de 30 días)
26/05/2026
  • El informe de drenaje está en proceso, las líneas de alcantarillado están siendo delineadas.
  • El paquete se completará en las próximas dos semanas
21/05/2026
  • Los planos se están finalizando para ajustar los planes de drenaje, regradas el terreno y reducir la cantidad de relleno necesaria para desarrollar.
  • 2 semanas para presentar nuestros planos para revisión
12/05/2026
  • El informe de drenaje (modelos de inundación) sigue pendiente para poder preparar el plat.
  • No tienen ningún plat mayor ni menor
05/05/2026
  • Actualizando el plan del sitio; la presentación al condado para revisión se realizará a finales de la próxima semana.
  • Dos lotes por diseñar (aprobación del plat, por lo que será más fácil con este diseño)
  • Wilson verificará si podemos realizar una aprobación de plat menor en lugar de una mayor (dentro de la ciudad de San Antonio para revisión, así que lo dejamos como está)
23/04/2026
  • El certificado llegará, ha sido aprobado.
  • El plat y el informe de drenaje están listos para enviarse (se espera tenerlos en una semana)
21/04/2026
  • A la espera de una actualización del departamento de bomberos para poder presentar al condado
  • Los planos están actualmente en 507 pads
07/04/2026
  • A la espera de la aprobación del departamento de bomberos para presentar al condado para revisión
  • Realizando cambios en los planos para volver a 501 pads en total
  • El contrato de agua está listo y se firmará
  • Propuesta a enviar por los cambios debido a la planta de tratamiento in situ (~menos de 30 $k)
  • La aprobación del departamento de bomberos sigue pendiente
  • El cronograma general sigue en marcha
17/03/2026
  • Estamos atendiendo los comentarios de los bomberos/prevención de incendios para la presentación (cambio de radio, hidrantes y dimensiones que deben mostrarse)
  • Después se presentará al condado
10/03/2026
  • El departamento de bomberos dio comentarios (radio de 28 ft para el derecho de vía y el carril de incendios)
  • Una vez realizadas las modificaciones, presentaremos con el condado
  • El pago por la revisión está pendiente
03/03/2026
  • Dos solicitudes separadas para las partes MH y RV del proyecto (tasas dobles: MH: 8 000  $ RV: 4 200 $)
  • 500 $ y 20 $/plaza adicional 50 $/hidrante (bomberos/prevención de incendios)
  • Aún hay tarifas por TIA, planos y revisión
17/02/2026
  • Se ha presentado el primer conjunto de planos, hoy me compartirán los planos (el miércoles tendremos claridad sobre la tarifa de revisión)
  • El contrato con Water USA está siendo redactado por Green Valley SUD
27/01/2026
  • Dar seguimiento a la USA for water para nuestra revisión
  • Plano y plat para ser presentados antes del viernes con los Fire Marshalls; una vez revisados y aprobados se enviarán al condado
  • Dar seguimiento con Green Valley para la USA for water
  • Plano de sitio revisado con estacionamiento del parque aclarado
  • Plan de protección contra incendios que fue re-presentado
  • Water USA está pendiente
13/01/2026
  • El plano del sitio revisado se presentó la semana pasada, el condado lo está revisando y debería confirmar esta semana la aprobación
  • Juego de planos a presentar antes de fin de mes, los fire marshals deben aprobar los planos primero
  • Presentar solicitud para la USA for water Green Valley Special District (Rudy hará seguimiento con ellos)
06/01/2026
  • Nos reunimos con el condado para revisiones de los planes, los cuales han sido presentados para revisión y están a la espera de aprobación
  • 492 lotes en total (pérdida de 4 lugares debido a cambios)
  • Conjunto completo de planos a presentar a fin de mes
16/12/2025
  • Se espera la presentación de los planes en enero
  • Proveer derecho de paso privado a los lotes interiores (retroceso de 25ft desde los campos sépticos, retrocesos de 10ft en frente y lateral)
  • El campo OSSF se volvería más pequeño
  • No se permiten RV frente a los derechos de paso de 70ft en Stagecoach (entrada por vías internas)
  • 40 GDP por cada séptico de RV
  • El comisionado se opone a nuestro tipo de desarrollo (anciano hablando de problemas futuros)
02/12/2025
  • La reunión de pre-solicitud de mañana 12/3 se traslada dentro de 2 semanas
  • Todavía se está trabajando en el diseño por terminar
18/11/2025
  • 496 lotes en total para dejarnos 2.5 acres para amenidades
  • Estamos a tiempo para la primera ronda de presentación a finales de enero
11/11/2025
  • Reunión con Guadalupe County el 3 de diciembre para discutir los planos
25/10/2025
  • El 90 % del drenaje está hecho, el estanque preliminar está en desarrollo
  • El estudio hídrico sigue pendiente
  • Actualmente 515 pads en total, plano del sitio a recibirse mañana
  • Fin de enero para la presentación del juego completo de planos
  • 504 pads en total
  • 2,5 acres para el área de amenidades reduce el total de pads a 496
  • A mitad de diseño de drenaje y estanque para trabajar en el plano del sitio
  • Presentación a finales de enero
11/09/2025
  • El estudio hídrico ha sido presentado; el pago llegará el 16 de septiembre
  • Los planos de construcción están en desarrollo
12/08/2025
  • La presentación del estudio hídrico se hará mañana
  • El condado ha dado comentarios sobre nuestros planos tras la pre-solicitud y aprobaría nuestro proyecto
  • Lote serie 900 (incorporar estacionamiento en el propio lote)
  • Parcelación de un right of way (carretera de 50ft de ancho, right of way de 70ft)
  • Carril de giro a la izquierda que sería requerido (mejorar la intersección hacia I10)
  • Se necesita permiso de desarrollo en llanura de inundación (CLOMR/LOMR solo si altera la llanura de inundación)
29/07/2025
  • Se debe presentar un plan de agua para el estudio hídrico (plan completo de servicios y distribución)
22/05/2025
  • Modelo hidráulico a terminar antes del final de esta semana
  • Retiro de 25 pies respecto a los linderos de la propiedad (servidumbre de acceso privada a cada lote individual)
  • Habría que ceder 35 pies (derecho de vía de 70 pies) desde el eje de la vía y 25 pies de retiro frontal
  • El propietario trajo un plano para vivienda unifamiliar (SFR) con varios sistemas sépticos en un mismo lote
  • No es necesario hacer el LOMR ni el CLOMR, solo se requerirá un estudio de inundación
  • Siguiente paso: estudio de factibilidad del agua, factibilidad séptica (mapas de suelos: arcilla negra)
  • Reducción a la mitad del campo del sistema séptico aeróbico (se excavarán 24 pulgadas de suelo, se importará marga arenosa para duplicar la tasa de infiltración) (se exigirá una reserva del 100 % para el sistema por goteo)

Disposition outlookPrepared in parallel — buyers take entitled and half-entitled projects

Projected exit · pro forma
Original projection · 4 475 810 $ net
Capital invested2 324 865 $
×1.9projected *
Producto neto de la cesión4 475 810 $
Operation net result — a 93 % project ROI2 150 945 $
Line by line
Projected disposition price· sale of the entitled land, per the pro forma7 079 800 $
Less selling costs· the gap between the registry's two figures — not itemised in the sources-2 603 990 $36.8 %
Producto neto de la cesión4 475 810 $
Less capital invested· project capitalization-2 324 865 $
Operation net result2 150 945 $93 %

* Projected figures from the pro forma (original projection): they are neither a promise nor a guarantee of performance. The estimated disposition date is the expected acquisition date plus the hold period.

The deal as the registry holds it
LQWealth Track Record.xlsx · as of 2026-09-18
Precio de reventa proyectado (neto)
7 079 800 $
Precio de venta neto
4 475 810 $
Beneficio neto proyectado
2 150 945 $
ROI del inversor
64 %
TIR del inversor
21 %
ROI del proyecto
93 %
Período de tenencia
24 - 36 M
Cronograma de venta
Q2 - Q4 2027

Fuente: LQWealth Track Record.xlsx › "Entitlements" · al 18/09/2026 — cifras dispo a menudo proyectadas, a validar

When — the sale timelines in the sources
The pro forma window governs

The estimated disposition date is the acquisition date plus the hold period; the LQWealth registry carries its own date and flags its disposition figures as projected, to be validated.

Surfaces that disagree
1 points for the team to reconcile
Sale timeline
Registry Q2 - Q4 2027 · pro forma window Q4 2027 – Q4 2028 (acquisition date plus the hold)
Pro forma governs

None of these changes the projected figures; each one is a field to align across the registry, the data room and the engineer's set so that every surface says the same thing.

What an investor getsPro forma, original projection — not a promise of performance

64 %Projected investor ROI — total profit on invested capital, over a 24–36 month hold.21 % target IRRPer 100 000 $ invested100 000 $Capital back64 000 $Projected profit164 000 $Projected totalArithmetic on the pro forma ROI of 64%, shown per 100 000 $ to make the scale readable. Projected — neither a promise nor a guarantee of performance.
How the net result is shared
Net result 2 150 945 $ · investors receive 1 496 877 $
1 · Return of capital· first, in full, from the net disposition proceeds2 324 865 $
2 · Preferred return· 10 % a year, paid before any profit is split697 460 $32.4 %
3 · Investor share of the residual799 417 $37.2 %
Total to investors· of the capital invested1 496 877 $64 %

Arithmetic on the pro forma (original projection). Neither a promise nor a guarantee of performance.

Project plans — evolutionfrom concept to final plan

The layout plan sharpens as entitlements progress: each version below reflects county and engineering feedback — value creation in motion.

PDFSite plan
Loading the plan…

Finances — on the recordRaise · seller financing · taxes · pro forma summary · costs paid

Raise100 %
Capitalización del proyecto2 324 865 $
Presupuesto total del proyecto4 649 730 $

Presupuesto = suma de las partidas del pro forma — cifras previsionales, por validar

Financiación del vendedor

Free and clear — no seller financing, no debt.

Fuente: RiseQuire Portfolio Promissory Notes Information.xlsx · 2026-09-18

Property taxes

Parcelas seguidas1
Taxes paid (current cycle)1/1 · 0

Fuente: Tax Payment Information.xlsx · 2026-09-07

Pro forma (summary)

Total Acquisition Costs1 146 250 $
Total Carry Cost42 000 $
Pre Acquisition540 000 $
Land Planning Total596 615 $
Total Equity Raise2 324 865 $

Fuente: RiseQuire Portfolio Pro Forma Overview.xlsx · 2026-09-10 — projected figures, to be validated

Pre-acquisition & entitlement costs

Enginering Work · LJA Engineering504 000 $
Taxes
Insurance
Total costs · paid 504 000 $504 000 $

Fuente: Portfolio Expenses.xlsx · 2026-09-15

Ownership & proofEntity · GP · management · the official county record

Who holds the land

State registry = entity ownership (the LLC) · county site = land ownership — two distinct official proofs.

1 record
1 open today
Proof #2 — land ownership
Sitio del county — ficha de la parcela

Registro oficial del county — Guadalupe County, TX.
APN : 68075 — paste into the county search

Documents & materialsData room · webinar replay · brochure

Investment presentation3 documents
PDFBrochure
XLS
PDFOwner's Title Policy - Police d'assurance titres du propriétaire2026-09-14
PDFSurvey - Levé 012026-09-14
PDFEnvironmental Site Assessment - Évaluation environnementale de site (Aug 2023)2026-09-14
PDFTopographic Survey - Levé topographique (Jul 2025)2026-09-14
PDFGeotechnical Engineering Report - Rapport d'ingénierie géotechnique (Dec 2025)2026-09-14
PDF- Title Policy2026-04-28
PDFGeotechnical Report2026-04-28
PDFDean Tract Waste Water Transmittal and Service Feasibility Study2026-04-28
PDFDean Tract Water Transmittal and Service Feasibility Study2026-04-28
PDFEXISTING SURVEY2026-04-28
PreviewPick a file — it reads here, in the page.
Nothing open yetPick a file in the middle column. PDFs render page by page; workbooks sheet by sheet.
Upcoming project documents
Each one joins the current documents once filed in the data room.
Preliminary layout & lot plan — revision 1Preliminary layout & lot plan — revision 2Preliminary layout & lot plan — revision 3Final layout plan — approved once entitlements are secured

QuestionsThe LandQuire team answers you directly on this page

Frequently asked
¿Cuándo recibiré mi K-1?
Su K-1 se prepara anualmente siguiendo un ciclo de borrador → revisión → versión final, con el objetivo de enviarlo antes de finales de marzo. Se le notificará tan pronto como esté disponible.2026-08-15
¿Cuándo y cómo se me distribuye después de una venta?
Después de la venta de un activo, las distribuciones siguen la estructura prevista en el contrato: retorno del capital invertido, luego el rendimiento preferente, y finalmente la distribución de la plusvalía (promote). El calendario y los montos exactos se le comunican en el momento de cada distribución.2026-08-15
¿Puedo convertir mi participación en otro portafolio?
Es posible bajo ciertas condiciones: una conversión requiere la firma de los documentos correspondientes. Nuestro equipo te acompañará caso por caso para validar la elegibilidad y formalizar la operación.2026-08-15
¿Por qué invertir en Estados Unidos?
Invertir en Estados Unidos ofrece numerosas ventajas, especialmente en el sector inmobiliario, que sigue siendo muy dinámico en estados de fuerte crecimiento como Texas y Nevada. Esta tendencia se ha acelerado desde la era pos-COVID, con la deslocalización de empresas, especialmente del sector tecnológico, desde estados con altos costes como California y Nueva York hacia la región del Sunbelt. Esta migración ha estimulado la creación de empleo y ha aumentado considerablemente la demanda de vivienda, lo que hace que estas regiones resulten especialmente atractivas para los inversores. Además, los precios de los terrenos en Estados Unidos se revalorizan de forma natural debido a la profundidad del mercado y a la abundancia de terrenos sin urbanizar. Por el contrario, Europa se enfrenta a una saturación del mercado inmobiliario y a una oferta limitada, lo que dificulta los proyectos de gran envergadura. El proceso administrativo en Estados Unidos también es más eficiente, con aprobaciones de permisos más rápidas que en Francia, donde los grandes proyectos de construcción —en particular los de gran altura— suelen implicar obstáculos burocráticos largos y costosos. Las inversiones inmobiliarias en Estados Unidos suelen ofrecer rendimientos más elevados, gracias a un régimen fiscal más favorable que en Francia. En los estados con un fuerte crecimiento, la escasez crónica de viviendas favorece la revalorización de los inmuebles. Por último, invertir en Estados Unidos permite diversificar la cartera gracias a la fortaleza y la estabilidad del dólar estadounidense, al tiempo que ofrece un marco jurídico seguro que garantiza una sólida protección de los derechos de propiedad.2026-09-14
¿Cómo seleccionan los terrenos para sus proyectos?
Seguimos una metodología rigurosa para seleccionar los terrenos destinados a nuestros proyectos, basándonos en un análisis exhaustivo de más de 120 criterios. Este enfoque nos permite identificar oportunidades de gran valor, al tiempo que garantizamos el cumplimiento de las políticas locales de urbanismo y desarrollo. Como empresa proptech, aprovechamos al máximo los datos abiertos sobre los propietarios de terrenos, lo que nos da acceso exclusivo a propiedades fuera del mercado que a menudo ofrecen una mayor rentabilidad. Nuestro proceso de selección comienza con un análisis a gran escala de los 3 216 condados estadounidenses, utilizando indicadores clave como el crecimiento demográfico en los últimos 10 años, el número de propiedades vendidas y en venta, y el tiempo medio de reventa. Al analizar datos procedentes de fuentes como Zillow y Redfin, nos centramos en unos cien condados donde la demanda es alta, la oferta es limitada y las propiedades se venden rápidamente. Una vez identificados los condados más prometedores, recopilamos los datos relativos a las propiedades y aplicamos un exhaustivo proceso de evaluación, analizando más de 100 000 parcelas al mes. Cada parcela se puntúa en función de factores como la topografía, la accesibilidad, la resistencia a las catástrofes naturales, la situación de la propiedad y el potencial de rentabilidad. Damos prioridad a las parcelas clasificadas como A- y B situadas en zonas suburbanas dinámicas con una gran conectividad en materia de infraestructuras. Además, los terrenos seleccionados deben ajustarse a nuestros objetivos ESG, minimizando el impacto medioambiental y garantizando un desarrollo sencillo, dando preferencia a terrenos llanos y con poca vegetación. Realizamos ofertas de compra estratégicas basadas en el valor estimado del terreno, adquiriendo propiedades a precios inferiores a los del mercado para garantizar márgenes de beneficio significativos. Por ejemplo, una parcela valorada en 100 000 dólares puede ser objeto de una oferta de entre 30 000 y 40 000 dólares. Este enfoque garantiza una fuerte revalorización, reforzada aún más por nuestros esfuerzos de mejora de los terrenos, que transforman parcelas sin urbanizar en activos muy atractivos y listos para su desarrollo. Nuestro proceso de evaluación tiene en cuenta factores como la ubicación, el acceso a las infraestructuras, la viabilidad económica y el impacto medioambiental. También colaboramos estrechamente con las autoridades locales para garantizar que nuestros proyectos se ajusten a los planes de desarrollo urbano. Siguiendo esta estrategia, respondemos eficazmente a la fuerte demanda del mercado, al tiempo que ofrecemos rendimientos sustanciales a nuestros inversores, en consonancia con las tendencias de los mercados en fuerte crecimiento.2026-09-14
Show 11 more
¿Qué tipo de proyectos desarrolláis?
Nos centramos principalmente en el desarrollo de terrenos residenciales para satisfacer la creciente demanda de viviendas. Sin embargo, también hemos emprendido proyectos hoteleros y de infraestructuras comerciales cuando se presentan oportunidades interesantes.2026-09-14
¿Por qué se centran en proyectos residenciales?
El mercado residencial responde a una demanda estructuralmente elevada, sobre todo a raíz de los cambios demográficos relacionados con la pandemia. Esta demanda constante garantiza una mayor estabilidad y un menor riesgo en comparación con otros segmentos, como los espacios de oficinas o los almacenes, que experimentan fluctuaciones más importantes.2026-09-14
¿Qué criterios medioambientales tienen en cuenta en sus proyectos?
Seleccionamos terrenos cuyo impacto medioambiental sea mínimo, dando prioridad a las parcelas con escasa vegetación y que no sean propensas a las inundaciones. Si es necesario talar árboles, lo compensamos con nuevas plantaciones y nos aseguramos de que se incorporen espacios verdes en nuestros proyectos para las familias que vivirán allí.2026-09-14
¿Quién lleva a cabo el análisis de la planificación urbana?
Colaboramos conLJA Engineering, una empresa que ha contribuido al desarrollo de más de10 000 viviendas al añoy que cuenta con una amplia experiencia en materia de permisos municipales. Gracias a sus estrechas relaciones con las autoridades urbanísticas de Texas, LJA es capaz de anticipar las restricciones normativas y estructurar los proyectos en consecuencia. Su experiencia nos ayuda a determinar el número de parcelas que pueden autorizarse, lo que nos permite optimizar nuestros proyectos antes de la adquisición. Al asociarnos con LJA, reducimos considerablemente el riesgo de que surjan problemas inesperados relacionados con la obtención de permisos, lo que nos permite avanzar con total confianza en proyectos bien planificados.2026-09-14
¿Cuál es la inversión mínima necesaria para convertirse en socio?
La inversión mínima para asociarse con nosotros suele oscilar entre 50 000 y 100 000 dólares, dependiendo del proyecto. Estos umbrales se han fijado no solo para garantizar la accesibilidad sin renunciar a unos estándares elevados, sino también debido a los requisitos normativos impuestos por las autoridades estadounidenses. A diferencia de un fondo de inversión tradicional, nuestros inversores participan directamente en proyectos específicos, lo que les ofrece una mayor transparencia y un mejor control sobre las oportunidades en las que deciden participar.2026-09-14
¿Ofrecéis oportunidades fuera del ámbito de los proyectos de suelo residencial?
Sí, aunque nuestra especialidad principal son los terrenos residenciales, también hemos trabajado en proyectos específicos, como hoteles y centros de datos. Exploramos constantemente nuevas oportunidades en función de las necesidades del mercado.2026-09-14
¿Cuál es la duración media de los proyectos que ofrecen?
La duración media de nuestros proyectos oscila entre 18 y 24 meses. Depende de la complejidad del proyecto y de su ubicación, pero nos esforzamos por ofrecer plazos realistas y óptimos con el fin de maximizar el retorno de la inversión.2026-09-14
¿Qué rendimiento puedo esperar de sus proyectos?
Nuestros proyectos ofrecen rentabilidades competitivas, a menudo superiores a las de otros tipos de inversiones inmobiliarias. Aunque los resultados varían en función de las características específicas de cada proyecto, nuestra rigurosa metodología garantiza beneficios interesantes para nuestros inversores. La tasa de rendimiento prevista, o ROI (Global Return on Investment), se calcula teniendo en cuenta todos los elementos clave de la operación. Esto incluye el precio de adquisición del terreno, así como los costes de ingeniería, desarrollo y acondicionamiento del terreno. Una vez superadas estas etapas, definimos legalmente el número de parcelas que se pueden dividir del terreno, respetando la normativa local. Posteriormente, la reventa se lleva a cabo a un precio unitario por lote basado en un análisis exhaustivo de los valores del mercado local. Tras deducir los gastos relacionados con la transacción, tales como los gastos de cierre y los gastos administrativos, se calcula el beneficio neto. Este rendimiento neto, que se comparte con nuestros inversores, ofrece una perspectiva de rentabilidad significativa al tiempo que cubre los costes inherentes a la operación. Nuestro enfoque estructurado permite optimizar el valor de cada proyecto, al tiempo que garantiza márgenes interesantes a nuestros socios financieros.2026-09-14
¿Cuáles son los riesgos asociados a este tipo de inversión?
Como cualquier inversión, existen riesgos inherentes. Sin embargo, los minimizamos mediante una selección rigurosa de los terrenos, la colaboración con expertos locales y un análisis exhaustivo de las oportunidades antes de comprometernos con un proyecto. En nuestro modelo, usted invierte en proyectos de desarrollo inmobiliario destinados a transformar terrenos sin urbanizar en parcelas listas para la venta. Este proceso incluye la adquisición del terreno, los estudios de ingeniería y la delimitación legal de las parcelas con vistas a su reventa a precios unitarios competitivos. Este modelo garantiza la transparencia y una inversión tangible respaldada por activos reales en cada proyecto. El mercado inmobiliario estadounidense, especialmente en estados como Florida y Texas, se caracteriza por una fuerte demanda. Nuestros proyectos de promoción responden a esta creciente necesidad, pero, como en cualquier mercado, pueden surgir ciertos riesgos: 1. Riesgo de retraso o disminución de las ventas Aunque prevemos precios competitivos, es posible que algunos lotes se vendan a precios más bajos en caso de una desaceleración económica o de una caída de la demanda local. Sin embargo, estos ajustes son poco frecuentes y, por lo general, no afectan al conjunto de las operaciones. 2. Fluctuaciones en los costes de infraestructura Los costes de desarrollo pueden, en ocasiones, superar las estimaciones iniciales. Para evitarlo, incorporamos márgenes de seguridad con el fin de absorber estas variaciones. 3. Modificaciones de la normativa local Los cambios en la legislación urbanística o las actualizaciones de las políticas locales pueden afectar a los plazos o a los costes. Minimizamos este riesgo colaborando desde el principio con los ayuntamientos y validando previamente la viabilidad de nuestros proyectos. Con más de 140 proyectos completados, adquirimos terrenos cuyo valor está preestablecido, lo que garantiza que puedan revenderse a precio de mercado, incluso en caso de ajustes. Medidas de mitigación de riesgos Sociedades de responsabilidad limitada específicas para cada proyecto: cada proyecto se estructura como una sociedad de responsabilidad limitada independiente, lo que permite aislar los riesgos. Si un proyecto se enfrenta a dificultades, esto no afecta a los demás, lo que garantiza la seguridad de la inversión. Tangibilidad de los activos a largo plazo: Los inversores poseen participaciones en una sociedad dedicada a cada proyecto específico. Si, al término del periodo contractual (aproximadamente cuatro años), quedan algunas parcelas sin vender, ofrecemos a los inversores la posibilidad de convertirse directamente en propietarios de dichas parcelas, lo que supone una garantía a largo plazo. Un modelo transparente y concreto Al invertir con nosotros, se convierte en accionista de una empresa dedicada a la adquisición y el desarrollo de terrenos. Nuestras operaciones de predesarrollo tienen como objetivo maximizar el valor de los terrenos, dejándolos listos para la construcción con las infraestructuras necesarias y las parcelas legalmente definidas de conformidad con la normativa local. Este activo tangible, del que usted es propietario a través de sus acciones, garantiza que su inversión está vinculada a una propiedad real y física. Compromiso con los inversores Nuestra prioridad es establecer relaciones a largo plazo con nuestros inversores, ofreciendo soluciones flexibles y maximizando la rentabilidad al tiempo que minimizamos los riesgos. Gracias a nuestra experiencia y a nuestra sólida presencia local, gestionamos de forma proactiva los posibles retos para garantizar el éxito de cada proyecto.2026-09-14
¿Pueden invertir en LandQuire los inversores de cualquier país?
LandQuire colabora con inversores de numerosos países de todo el mundo. No obstante, la elegibilidad de los inversores está sujeta a las leyes y normativas estadounidenses aplicables, incluidas las sanciones económicas y comerciales impuestas por la Oficina de Control de Activos Extranjeros (OFAC) del Departamento del Tesoro de los Estados Unidos, así como a los requisitos aplicables en materia de KYC y LAB. LandQuire no acepta inversiones procedentes de particulares, entidades o jurisdicciones en las que la inversión esté prohibida o restringida en virtud de las leyes o normativas sobre sanciones aplicables. Además, es posible que se excluyan determinadas jurisdicciones en virtud de las políticas internas de cumplimiento normativo y gestión de riesgos de LandQuire. Todos los inversores potenciales se someten a una verificación de cumplimiento, y la elegibilidad definitiva se determina durante el proceso de incorporación.2026-09-14
¿Ofrecen garantías a los inversores?
Garantizamos una transparencia total en nuestros procesos, así como contratos claros y detallados diseñados para proteger los intereses de nuestros inversores. Estos son los elementos clave que garantizan la seguridad y la fiabilidad de nuestros proyectos: 1. Propiedad inmobiliaria LandQuire es propietaria del terreno de cada proyecto. Al invertir, los inversores obtienen una garantía tangible en forma de acciones de una sociedad que posee un activo inmobiliario. 2. Seguro de propiedad Todos los terrenos adquiridos están asegurados, lo que ofrece una protección adicional frente a imprevistos. 3. Una trayectoria demostrada Nuestra trayectoria demuestra nuestra capacidad para gestionar proyectos de forma eficaz y generar rendimientos interesantes para los inversores. 4. Acciones preferentes para los inversores Los inversores reciben acciones preferentes, que les otorgan derechos prioritarios sobre los beneficios y los repartos. 5. Asignación exclusiva de los fondos Nuestros contratos garantizan que los fondos recaudados se destinen exclusivamente al proyecto específico, lo que elimina el riesgo de dilución o de reasignación imprevista. 6. Dinámica del mercado Aunque no se trata de una garantía formal, operamos en mercados estratégicos, como Florida, donde la fuerte demanda de terrenos y viviendas favorece la revalorización de nuestros activos. Estas medidas no sustituyen a una garantía total, pero refuerzan considerablemente la solidez de nuestros proyectos. Ofrecen a los inversores un alto nivel de seguridad basado en activos tangibles, procesos rigurosos y un posicionamiento estratégico en mercados atractivos.2026-09-14

TraceabilityEvery field, its source and its date

CampoValorSourceAs ofConfianza
Etapa / estadoUnder MgmtLQWealth Track Record.xlsx › "Entitlements"18/09/2026Registro LQWealth (Track Record)
Fecha de adquisición29/10/2025Closing statement (data room)Décompte de clôture (data room)
UbicaciónMarion, TXLQWealth Track Record.xlsx › "Entitlements"18/09/2026Registro LQWealth (Track Record)
Documentos de la data roomfolder updated 04/03/2026SharePoint (LQDataRoom)04/03/2026Archivos

Source: LQWealth registry + Willem files · automatically refreshed from LandQuire internal files and tools, several times a day · read-only.