LQPF11 · Elmendorf, Texas · 49 acres (19.83 ha · 198,300 m²)

Mobile Home Park · LQ INVESTMENTS PORTFOLIO ELEVEN LLC

Home
LandQuire desk

The landSatellite · LandID · Google Maps · Photos — and the progress at a glance

3D terrain
Click two points to measure · layers top right
✓ LandQuire owned
LQ INVESTMENTS PORTFOLIO ELEVEN LLC
✓ LandQuire owned
LQ INVESTMENTS PORTFOLIO ELEVEN LLC
Satellite + boundaries · parcel in yellow · measure the distance to sewer, road or schoolEsri, Maxar, USDA · OpenStreetMap

49 acres (19.83 ha · 198,300 m²) of raw land · Elmendorf, Texas · 360 lots projected · Mobile Home Park

Project progressInstaGantt · 2026-09-20
76%Overall project progressrefreshed every 3 h
56Total tasks39Completed17Remaining
100%Surveyingrefreshed every 3 h
4Total tasks4Completed0Remaining
100%SAWSrefreshed every 3 h
5Total tasks5Completed0Remaining
67%Bexar Countyrefreshed every 3 h
6Total tasks5Completed1Remaining
Current milestoneTCEQ approval on the WWTFEst. timeframe: December 2026Milestone progress35%
100%COSA Technical Reviewsrefreshed every 3 h
10Total tasks10Completed0Remaining
100%Letters of Certificationrefreshed every 3 h
5Total tasks4Completed1Remaining
Current milestoneSAWSEst. timeframe: September 2026Milestone progress95%
100%Pre-Listingrefreshed every 3 h
3Total tasks0Completed3Remaining
Current milestoneDetermine if Selling with a broker or withoutEst. timeframe: July 2025Milestone progress0%
50%Marketingrefreshed every 3 h
6Total tasks0Completed6Remaining
Current milestoneMail Brochure to 50 to 100 Builders (preferred buyers)Est. timeframe: February 2027Milestone progress50%
100%Broker Listingrefreshed every 3 h
1Total tasks1Completed0Remaining
0%Projected Salerefreshed every 3 h
1Total tasks0Completed1Remaining
Current milestoneSale between Q3-Q4 2026Est. timeframe: December 2026Milestone progress0%
0%Closing Salerefreshed every 3 h
3Total tasks0Completed3Remaining
Current milestoneOffer SignedEst. timeframe: December 2026Milestone progress0%

Progress, task counts and target dates come from the team’s InstaGantt export, picked up automatically every 3 hours. Dates are planning targets, not commitments.

Q3 2026 – Q3 2027Disposition — resale windowPrepared in parallel · projected net result $1,764,000*
100%Funded & acquiredProject capitalization $2,384,000 · Land acquired on July 22, 2024

* Projected figures from the pro forma (original projection) — neither a promise nor a guarantee of performance. Progress and milestones: InstaGantt export of September 20, 2026. Capitalization and disposition: LQWealth registry of 2026-09-18.

Where it standsFunded · value-add underway · disposition prepared in parallel

Project phase
Land acquired 2024-07-22 · last permit target February 2027 · resale window Q3 2026 – Q3 2027
Value-add — entitlement 76% complete

In the value-add phase, the 4 markers track the land acquisition and regulatory progress.

Team notes — 4 markers
Team weekly note · 2026-09-03
Acquisition documentsIn progress

SAWS agreement to be signed and recorded (contract pending)

SourceStated by Willem · in progress · LandQuire team update · July 2, 2026
Entitlement progressIn progress

Due diligence in progress; reviews and regulatory comments remain open

SourceStated by Willem · in progress · LandQuire team update · July 2, 2026
Land acquiredConfirmed

Land acquired on July 22, 2024.

SourceInferred from stage (registry) · LandQuire team update · September 18, 2026
Recent activityConfirmed

USA draft is being finalized and will be internally reviewed for the next week, until it will be sent to us

SourceStated by Willem · confirmed · LandQuire team update · September 3, 2026
Key dates
On file, then the schedule
Land acquired
LQWealth registry
2024-07-22
Last permit target
List on Costar Lands of America and other websites · InstaGantt
February 2027
Resale window
Hold period on the LQWealth registry
Q3 2026 – Q3 2027
LQPF11 · Under Mgmt · LQ INVESTMENTS PORTFOLIO ELEVEN LLC

Surveying 100% · SAWS 100% · Bexar County 67% · COSA Technical Reviews 100% · Letters of Certification 100% · Pre-Listing 100% · Marketing 50% · Broker Listing 100% · Projected Sale 0% · Closing Sale 0%.

Entitlement tracking · 70 permit lines · 48 completeExport September 20, 2026

Latest weekly note · 2026-09-03

USA draft is being finalized and will be internally reviewed for the next week, until it will be sent to us
One final drainage comment that has been addressed, right of way department is the final department for an approval
Completion report is being worked on to make sure all the reviewers have all the documents needed
Up next — from the project schedule
Bexar County
December 2026TCEQ approval on the WWTF
Letters of Certification
September 2026SAWS
Marketing
February 2027Mail Brochure to 50 to 100 Builders (preferred buyers)
February 2027Phone Call Follow ups with preferred buyers
February 2027Tailored Email blast to builders/investors/ Developers few
February 2027A hundred to over 1000 regional and national investors outreach
February 2027Phone Call & Email to Builders/ Investors
Projected Sale
December 2026Sale between Q3-Q4 2026
Closing Sale
December 2026Offer Signed
December 2026Closing Date
December 2026Wire Received
Unphased
December 2026Plat Recordation
$2,384,000Capital invested
48%Projected investor ROI *
16%Projected investor IRR *

* Pro forma, original projection — LQWealth registry. Neither a promise nor a guarantee of performance.

The latest plan — Site planSee the plans
A question about this deal?
The LandQuire team answers you directly on this page.
Ask a question

Entitlement updatePermit tracking · InstaGantt · weekly notes

Permit tracking — all 70 lines
76% complete
Current reviewTCEQ approval on the WWTF35% · target December 2026
Lines7048 complete · 19 upcoming · 3 overdue
Next targetsSeptember 2026 · December 2026
Permit tracking — line by line, on the calendar
Hover a bar for start, duration and target
Task · start · duration%
JulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMay
Target
Labus Manufactured Home ParkJuly 2024 · 3 months 4 days
100%
October 2024
SurveyingJuly 2024 · 3 months 4 days
100%
October 2024
BoundaryJuly 2024 · 17 days
100%
August 2024
TopographicAugust 2024 · 5 days
100%
August 2024
TreeAugust 2024 · 12 days
100%
August 2024
Subdivision PlatSeptember 2024 · 2 months
100%
October 2024
Conceptual PlanAugust 2024 · 12 days
100%
August 2024
Country MeetingSeptember 2024 · 5 days
100%
September 2024
COSA MeetingSeptember 2024 · 5 days
100%
September 2024
Plans and ReportsSeptember 2024 · 2 months 5 days
100%
November 2024
Site Development PlansSeptember 2024 · 2 months 5 days
100%
November 2024
Traffic Impact AnalysisSeptember 2024 · 2 months 5 days
100%
November 2024
Storm Water ManagementSeptember 2024 · 1 month 12 days
100%
October 2024
Public Water Main ImprovementSeptember 2024 · 1 month 12 days
100%
October 2024
Detention Pond DesignSeptember 2024 · 1 month 12 days
100%
October 2024
Tree Mitigation PlanSeptember 2024 · 2 months 5 days
100%
November 2024
SWPPPSeptember 2024 · 1 month 12 days
100%
October 2024
SABuild Development ServiceSeptember 2024 · 2 years 3 months 12 days
100%
December 2026
SAWSSeptember 2024 · 4 months 18 days
100%
February 2025
USASeptember 2024 · 4 months 18 days
100%
February 2025
Water QualityOctober 2024 · 3 months 20 days
100%
February 2025
SepticOctober 2024 · 3 months 20 days
100%
February 2025
WaterOctober 2024 · 3 months 20 days
100%
February 2025
AquiferOctober 2024 · 3 months 20 days
100%
February 2025
Bexar CountyNovember 2024 · 2 years 1 month 16 days
67%
December 2026
TrafficNovember 2024 · 1 month 6 days
100%
December 2024
General PlattingNovember 2024 · 3 months 4 days
100%
February 2025
TCEQ approval on the WWTFNovember 2024 · 2 years 1 month 16 days
35%
December 2026
Storm DrainNovember 2024 · 1 month 6 days
100%
December 2024
Flood PlainNovember 2024 · 1 month 6 days
100%
December 2024
Driveway PermitNovember 2024 · 1 year 6 months 11 days
100%
May 2026
COSA Technical ReviewsOctober 2024 · 4 months 18 days
100%
March 2025
Office of Historic PresOctober 2024 · 1 month 17 days
100%
December 2024
Parks and RecreationOctober 2024 · 1 month 17 days
100%
December 2024
AddressingOctober 2024 · 1 day
100%
October 2024
SubdivisionOctober 2024 · 1 month 17 days
100%
December 2024
Habitat CompletenessOctober 2024 · 1 month 17 days
100%
December 2024
TCI - Storm WaterOctober 2024 · 4 months 18 days
100%
March 2025
Engineering TIAOctober 2024 · 1 month 17 days
100%
December 2024
Engineering TreesOctober 2024 · 4 months 18 days
100%
March 2025
CPS ROWOctober 2024 · 4 months 4 days
100%
February 2025
TCI - TIAOctober 2024 · 4 months 18 days
100%
March 2025
Letters of CertificationOctober 2024 · 1 year 11 months 20 days
100%
September 2026
SAWSJanuary 2025 · 1 year 8 months 11 days
95%
September 2026
Bexar CountyFebruary 2025 · 8 months 7 days
100%
October 2025
Office of Historic PresOctober 2024 · 4 months 23 days
100%
March 2025
Parks and RecreationOctober 2024 · 4 months 28 days
100%
March 2025
DSDApril 2025 · 22 days
100%
May 2025
Plat RecordationApril 2025 · 1 year 8 months 19 days
95%
December 2026
DispositionOctober 2024 · 2 years 7 months 27 days
50%
May 2027
Pre-ListingOctober 2024 · 9 months 12 days
100%
July 2025
Determine if Selling with a broker or withoutOctober 2024 · 8 months 27 days
0%
July 2025
Gather Due Diligence Material and create DD package for saleJuly 2025 · 4 days
0%
July 2025
Property Brochure CreationJuly 2025 · 9 days
0%
July 2025
MarketingJuly 2025 · 1 year 7 months 14 days
50%
February 2027
Mail Brochure to 50 to 100 Builders (preferred buyers)July 2025 · 1 year 7 months 14 days
50%
February 2027
Phone Call Follow ups with preferred buyersJuly 2025 · 1 year 7 months 8 days
50%
February 2027
Tailored Email blast to builders/investors/ Developers fewJuly 2025 · 1 year 7 months 7 days
50%
February 2027
A hundred to over 1000 regional and national investors outreachAugust 2025 · 1 year 6 months 16 days
50%
February 2027
Phone Call & Email to Builders/ InvestorsSeptember 2025 · 1 year 5 months 25 days
50%
February 2027
List on Costar Lands of America and other websitesSeptember 2025 · 1 year 5 months 24 days
50%
February 2027
Broker ListingFebruary 2026 · 1 year 3 months 10 days
100%
May 2027
List Property w/ Broker Q2-Q3 2025February 2026 · 1 year 3 months 10 days
100%
May 2027
Projected SaleJuly 2026 · 6 months 4 days
0%
December 2026
Sale between Q3-Q4 2026July 2026 · 6 months 4 days
0%
December 2026
Closing SaleJuly 2026 · 6 months 4 days
0%
December 2026
Offer SignedJuly 2026 · 6 months 4 days
0%
December 2026
Closing DateJuly 2026 · 6 months 4 days
0%
December 2026
Wire ReceivedJuly 2026 · 6 months 4 days
0%
December 2026

export 2026-09-20 · InstaGantt

Update history — team weekly notes
2026-09-03
  • USA draft is being finalized and will be internally reviewed for the next week, until it will be sent to us
  • One final drainage comment that has been addressed, right of way department is the final department for an approval
  • Completion report is being worked on to make sure all the reviewers have all the documents needed
2026-08-27
  • City has approved our drainage plans, the county still has a week to review our plans
  • SAWS finished their model on the capacity that our project requires
  • The site development permit has been submitted for review by the county
  • An onsite meeting is scheduled for next week to discuss the location of the onsite Wastewater Treatment Facility
2026-08-11
  • Tree mitigation plan was approved, which brought the tree permit down to $0 to $196k
  • Been going back and forth with SAWS on changes, hoping to receive the USA very soon
  • All drainage departments comments were addressed and submitted end of last week, expecting a response pretty quickly
  • Project coordinator is working on the application process for site development permit
See full history (+71)
2026-07-31
  • LJA will follow up with the city on our submittal and feedback from the drainage department
  • Once the contract is approved, it will be presented to their board for official approval
2026-07-28
  • Application for site development permit will be submitted by next week
  • Working through comments from SAWS on the water contract, expected to take a couple of weeks
  • Expecting an update from Lauren on the WWTF this week on the application submittal
2026-07-23
  • Approved by mid-September
  • Only drainage department that is left with
  • Landscape architect work to be started
  • Submit for the site development permit (might be contingent on Plat approval), timeline to be submitted by next week, 30-day review period, most important part is drainage comments
  • Having the permit, you can start grading the site and build the channel and detention pond
  • Plat approval pending based on TCEQ approval for the WWTF
  • SAWS contract comments will be addressed and submitted today
  • Letters of certification is a formal approval but no written records
2026-07-15
  • Plans are submitted and under final review
  • SAWS is drafting contract
  • Up to 60 days to finalize entitlement
  • 347 lots (confirm ratio between different pad lots)
2026-07-07
  • Resubmitting the drainage plans today based on the 5 comments we received
  • SAWS had 2 comments on water, so revisions are being made
  • The layout and location of the facility are being finalized (Lauren)
  • Answer on Thursday for remaining timeline
  • Tree plan will be done by an external
2026-06-23
  • 350 lots (maxxed out) to make the irrigation area required for the project
  • Latest site plan will be submitted by Monday for the final review
  • Expecting the latest review for the plans, only for drainage report it might take longer depending on comments
  • Waiting for comments from SAWS on USA draft
2026-06-16
  • Drainage comments were worked on, and approval should be received soon
  • Proposal for tree and irrigation plan (landscape architect)
  • CPS need to do an upgrade offsite to their grid to provide power to our project (CPS will pay for it, not us) --> timeline is still unknown (75% of capacity is there)
  • CPS approved the plat
  • Waiting for an update from SAWS on the USA for water
2026-06-02
  • Lauren to confirm if she can find 5 acres
  • Additional study on the drainage is requested for a report
  • Treatment Facility vs Septic
  • Triggering setbacks and right of ways to split up into multiple lots instead of two lots
  • Timeline for TCEQ approval
  • Irrigation vs leach field/septic system area needed
2026-05-28
  • We met all the requirements for the minor plat which was approved
  • Drainage reviewer rejected our requirements (100 acres draining through our site), our channel and pond are public improvements
  • Get the major plat approved and signatured, without the TCEQ approval for an approval (would expire in December) --> Waiting for the TLAP
  • Expecting 30-45 days to be approved
  • Cheaper to pay the fee for the tree mitigation (planting trees and irrigation would cost more than the fee)
  • 11 acres for irrigation needed, currently only 6 acres (150ft from boundary of the property)
2026-05-26
  • Back and forth with drainage
  • Waiting for an update from Lauren on WWTF
2026-05-21
  • Under review with the city, explaining the changes made (60
  • Drainage comments will come in on 6/5
  • USA from SAWS still to come in end of July
  • Expecting that the plat wouldn’t be approved without the easement or show the effort that we are working on obtaining it
  • Application to be submitted (to be confirmed what is included in the application)
2026-05-05
  • Labus fees for minor plat to be paid
  • SAWS is working on updating the USA, expecting to be done with USA to be signed by the end of July
  • Minor plat submittal has been done, once payments are in, they will start reviewing
  • Drainage will be the last part, but we have already gone to their previous comments
  • We have the same reviewers as previously, so we won’t be receiving the same comments as those have already been addressed
  • Still working on the easement of the neighbor (part of the drainage comments previously)
  • When we go to site development permit, we have all the information gathered (would be given once the wastewater facility is approved)
2026-04-30
  • Minor plat PDF to come in for Mathis as well
  • Up to 3 months to get the USA contract updated, approved and signed
  • Turnaround time on the plat approval is also another 3 months
2026-04-24
  • 8 months minimum for approval, public hearings for permitting approval (all neighbors are being notified)
  • Build a lot within our property so we would be the only neighbors, but this would need to be changed (minor plat application to be submitted, doesn’t go through the board, only an approval by the director of development)
  • Minor development permit plat --> TCEQ approval is needed for a major plat permit to then get the site development permit
2026-04-21
  • Plans are still under review
  • Comments on the hydrology report came in first (next items will be received after)
  • SAWS agreement needs to be recorded (we will need a revised version due to changes) --> number of EDUs need to be increased from 308 to 370 EDUs
  • Meeting with CPS for the design and capacity of the project
  • The design of it will be started and we are exploring options for irrigation and discharge of the system
2026-04-09
  • LJA is working on an easement needed from the neighbors (drainage analysis to be done to determine exact dimensions of the easement) --> proof of doing our best effort to get the easement, without it the city cannot cause issues if the seller doesn’t want to give it to us
  • LJA has someone in house to get started on the permitting and designing of the treatment facility
  • Plans are still under review
  • Easement might be the only reason for a slight delay
  • End of next week from Aquastore on the system
2026-03-17
  • Revising water and sewer lines (2 weeks out from updated plans)
  • Roads to be updated to meet requirements
  • The process for permitting is being started with Aquastore
  • Plans are done and will be submitted tomorrow (Friday)
  • Sewer design is done, treatment facility permits will be started on (6 months' timeline)
  • Plans have been submitted at the end of March
  • Coordination with TCEQ for their approval process and permit submittal (2-6 months)
  • Everything will be approved besides the plat until TCEQ approval is in
  • Proposal for landscape plan and irrigation is being worked on
  • Comments on clarification on drainage for pump systems
  • No expectation to receive comments on driveway and access
  • Driveway permit was approved
2026-03-10
  • Redesign is in the works (2-3 weeks from 3/9)
  • Review the Wastewater Treatment Quote and see if we have questions for them
2026-03-06
  • $30k additional fee for the redesign
  • Cannot go above 360 pads but will resolve right of way
  • Electrical easement outside of the right of way
2026-03-03
  • Possible fee for additional work
  • Additional 2-3 weeks to redesign the overall plans, profiling of the sewer lines, plat needs to be changed without IDPs
  • Get started on the permitting
  • No sidewalks and cheaper septic solution to build (What is the cost for the lift station)
  • Final Permit from CPS is pending as they are working on their design
2026-02-24
  • Setting up a meeting with this week to work on comment for driveway (county doesn’t want to maintain the interior roads)
  • We would need to discuss with SAWS about the sewer treatment plant (Rudy to call Tracy)
2026-02-19
  • Plans were submitted for review (Plans to be sent to me)
  • Septic Revisions are updated today
2026-02-17
  • Finishing up IDPs to submit everything tomorrow
  • Septic Design plans (dig 30inches of soil, 23,000 yards per septic field which would help us save dirt)
  • Preparing submittals for all the plans
  • Public vs private right of way approval is pending
2026-02-10
  • Discussion with the city was held last week about right of way and IDP
  • IDP means they want a public right of way --> answer to come in today or tomorrow
  • All tracks are to function together as one park (it was split up due to septic reasons)
  • Once approved, the final set of plans will be submitted this week
  • Application for the updated septic design will be in by Thursday
  • Expecting to be done in 30 days (bonding process 60 days, construction can be started prior)
2026-01-27
  • Final site plan to be submitted by Friday
  • Septic Design is still under review
2026-01-20
  • Septic Design will be done today, can be bid after
  • Meeting with the city reviewer to discuss latest plan (timeline TBD on Thursday)
  • 1 IDP instead of 20 IDPs as the city would not allow that and want this to be built in 1 piece
  • Internal sidewalks are requested, we would apply for a variance if needed
  • Final plans to be submitted next week (30 days to review and get approved)
2026-01-13
  • Addressing comments on driveway and grading to be submitted within the next week for final submittal and review --> 3-week turnaround time for review from the city (mid-February to be fully approved)
  • Design and plans were done --> have to check on permit application and review --> to be submitted and reviewed by city and TCEQ (30 days for feedback and 30 days for approval)
  • The intake person at CPS is distributing it to the design team for the upgrade on the electricity line from a single to three phase (timeline TBD)
2026-01-08
  • Change of entrance layout increase the curbs
  • Time home section close to the amenity center (deeper turn lane for fire lane, we will fight this)
  • Goal for next Tuesday to get the changes done (including grading)
  • Driveway permit comments are on there as well
  • Septic design will be done today
  • Easement to be added on the plat for CPS (infrastructure to be determined) --> single phase to three phase upgrades potentially needed
  • 2.4MW estimated to be needed for our project
2026-01-06
  • No approval or denial from the county on the driveway permit --> expected timeline to be done this month
  • Plans are still under review by the county (mainly drainage) --> submitted in December
  • Ready for bidding in beginning of February
  • Septic design is done and ready for bidding (to be send by LJA to us)
2025-12-16
  • We have received comments on variance application and site plan, should be fully approved by mid-January
  • Septic design is done and will be send over to us this week
  • Drainage comments came in, revised plans were submitted
2025-12-02
  • Septic design is not finished yet but will be done by Thursday
  • Confirmation on variance application and progress
  • Comments on final design should be in this week
2025-11-18
  • Septic design for 4 of them will be done by Thursday
  • Application fee of $350 for the variance application for the driveway, expecting an answer within 30 days
  • Electricity application was submitted with CPS, meeting is set on January 8th (design for them), plat and construction permit are not affected by this.
2025-11-05
  • The final set of plans was submitted for final review with the county
  • In the next 2 weeks the septic design will be completed for 24 different systems
  • CPS meeting is being scheduled
  • No further updates on the driveway variance application
  • Expecting to be fully approved in the next few weeks
2025-10-23
  • Variance application for driveway was submitted
  • Final site plan will be in by Monday, Septic plans as well
  • Plans will be done by tomorrow for bidding
  • CPS meeting is being set (no allocation needed but design standard) --> enough power, distribution to be confirmed
2025-10-16
  • Site and Septic plans are being done today
  • Power of Attorney for the USA to be signed on our behalf
  • Upload the variance for the driveway permit to start the process
  • Plans including septic will be submitted this week with 30-45 days to review
2025-10-14
  • Some minor drainage issues (cross sections are needed for the head grass), to be done by Thursday
  • Jose will get in contact with the commissioner for the variance of the driveway permit
  • Preliminary tank sizing (contact for septic installer from Jose) will be in by Thursday
  • Construction can be started in the next 60 days
  • $140k fee to be paid when we record the plat and water
  • 30 days for fire marshals to approve the vertical designs
  • Meeting with CPS is being scheduled for electricity onsite
2025-09-23
  • I am trying to get in contact with the commissioner for the driveway permit
  • Approved but still need approval from the commissioner's court, go into construction without a recorded plat (fully entitled) for a 2-year timeframe (recording can be done within 30-45 days)
  • Wednesday next week, the septic design will be sent over
2025-09-16
  • Plans are still under review
  • Our driveway is 30ft (40ft pavement instead for access) for 100ft at the entrance
  • Still waiting for feedback from SAWS on the USA request for the $140,000 payment for the waterline upgrade
2025-09-11
  • Ask Jose for update on driveway variance application
  • Framework has been set up for septic design, will need to be finalized to be submitted (timeline TBD – 2 weeks most likely)
  • Following up on USA for $140,000 payment moment
  • Drainage comments are still pending, waiting for approval
2025-09-09
  • Driveway variance for permits will be submitted today, potential for widening the entrance (affordable housing project)
  • USA is still being reviewed with our feedback about the time needed to be paying the $140,000
2025-08-19
  • Detention pond moved up by 1,5 inches
  • Plans will be sent out to me today
  • Variance application will be submitted tomorrow for driveway permit
2025-08-12
  • Plans will be received today
  • 30 day review for our final site plan
  • This week the septic design and (12,000 gallon 6 tanks) --> Power off a meter or solar panels
  • Apply for a variance for the driveway locations for the permits (further apart than current plans)
2025-08-05
  • Driveway is being finalized, will have plans in tomorrow
  • Once approvals are in, we will record the plat
  • 30 days for septic permits to be received
2025-07-29
  • Detention and plans are being finished and should be in by 7/30 so we can work on bids
  • Variance application is still pending
2025-07-10
  • Review has been completed, only working through drainage revisions (including general septic)
  • OSSF permit can be hold off until construction, conversation will be held next week for septic
  • Variance is still being reviewed (should have an answer latest by the end of last week)
  • 95% approved plans by next week for construction so we can start getting bids for construction
2025-07-03
  • Drainage comments came back that are being worked through
  • SAWS is still reviewing our variance application
2025-06-26
  • Variance application has been submitted with the county
  • Minor comments by the city on our site plan submittal are being worked on by LJA
  • Once the plans are approved, the septic engineer will work on septic designs
2025-05-29
  • Next week a meeting with SAWS is set up to discuss the variance application
  • Waiting for a bid for the water extension on the 1604 Loop to connect the 12inch to the 60inch on the South (about $400k)
2025-05-20
  • Variance letter will be sent to SAWS this week for not putting in a redundant waterline
  • Our plans have been submitted yesterday for second round of review (30-45 days for review)
2025-05-08
  • Meeting with the design team was held this morning and is completed which will be sent to us by Monday as well
  • Submittal will be done with the county by Monday
  • Waiting for feedback from SAWS on cost and application process for the water access
  • Alternative for water: looking to extend the 16inch on the East of us which would require an easement from the neighbor
2025-05-01
  • Site Plan Design is 95% done (redid drainage and streets) and will be submitted on Monday
  • Waiting for information on the variance application with SAWS for the waterline
2025-04-28
  • Site plan will be completed by the end of the week to be submitted next week
2025-04-22
  • Redesign will be done today, and the full layout will be ready for submittal next week
  • SAWS is requiring us to put in the redundancy waterline, we will apply for a variance and petition our case not having to put in the line
2025-04-18
  • We need to go to the board of SAWS to discuss the watermain upgrade they are requesting (credits to build the line for impact fees), we should get an update on this next week
  • Meeting Monday afternoon to discuss plan changes before next submittal
  • Spray field instead of a leach field to reduce the total area to increase the number of pads
  • Losing 10 pads because of pond increase, could decide to do tiny homes
2025-04-10
  • City is requesting that we detain our project (the pond would need to be larger from 1 to 3 acres (approx. 15 lots would be lost because of it)
  • Pump in the pond for in and out ($180,000 in expenses for the pump/lift station vs $240,000 in lost in lot values)
  • Submit new site plan for review with the city
  • No updates on Waterline redundancy lines as of now, need feedback on this ASAP
  • Construction cost could go up by $2000/lot
  • We will engage with the septic engineer once we have the approvals from the city
2025-04-03
  • New Drainage layout has been completed, with the amenity center on the south
  • Submit new site plan mid next week for review
  • No updates on Waterline redundancy line
2025-03-28
  • Comments on drainage, moving the amenity center next to the retention pond
  • Roads cross section needs to be added onsite
  • LJA will follow up with SAWS on the watermain
  • TCEQ rules, we might not put it in
  • Waiting for an update on the bid from Jack, expecting to get it by Monday
2025-03-20
  • Drainage comments back, the retention pond needs to be next to the amenity center so we will move the amenity center to keep the same layout
  • Watermain no updates from SAWS, following up
  • First bid received, Jose will review it
2025-03-13
  • Meeting with SAWS next Monday their drainage department for the redundancy of the existing waterlines
  • Next week we will have comments back from the county
  • Jack is a contractor putting together a bid for this project by next week
2025-03-06
  • Waiting on comments from the county
  • Waiting for answer from SAWS for water, Jose is pressuring them to give an update
  • 2 more weeks for county to review (submitted on 2/21), week of the 24th
2025-02-27
  • LJA met with SAWS to discuss potential revisions to the current waterlines with an upgrade that might be needed. We are expecting to hear back from them end of next week. $500,000 potential additional expense for construction if this upgrade is needed for a 3,000 LF line to be put in (redundancy mainline), utility right of way permit would be needed
2025-02-20
  • 40 comments from drainage review
  • SAWS/USA might require us to decrease our water usage so we might have to swap MH pads for tiny homes
  • Planting and irrigation plan to be submitted for the building permit
  • City review process has been completed, going through the Bexar County review process next, 1 month out from their review period
  • Septic engineer will need up to 1 month to complete the design (not needed for the platting)
2025-02-13
  • Comments came back on second review for water, main water line that would need to be extended but USA approved it without
  • Rudy will work on getting the preliminary Geotech report this week
  • We are missing the TCI – Stormwater, SAWS sign off on septic feasibility (LJA needs to submit feasibility letter) and Bexar County is waiting on the Geotech to sign off on our plans
  • Scheduled to complete entitlement beginning of June (1 month behind on original date)
  • Preliminary Geotech was received and submitted for review
2025-02-06
  • Preliminary Geotech will come in this week to submit with the county
  • TIA is in
  • Water comments made us on hold, USA issue has been addressed and a waterline to be put in was not needed
  • Drainage review is still pending
2025-01-23
  • Drainage review is still pending, comments back on water
  • Geotechnical report is the final piece needed for the plans
  • Once plans are approved by the city/county, we will engage with the septic engineer
  • Final review stages are coming up at the end of the month
  • Ready to break ground end in the middle of Q3
2024-12-19
  • Waiting on SAWS for the water contract either before Christmas or in the new year
2024-12-12
  • Comments by the city (18 reviewers):
  • Drainage and Traffic will be reviewed at last (End of January)
2024-12-05
  • The plat was submitted, payment went through, the full plans were submitted. 30-45 days for review
  • The project won’t have any progress during review
2024-11-14
  • QAQC process is pending
  • Next Wednesday they site plan will be submitted for review
  • 11/21 - Site plans will be submitted before the weekend
  • Drainage report needs to be finished for the full submittal
  • Pay the fees and wait for the review
  • Send it out to GCs and get a quote for the cost of construction (RFIs)
2024-11-07
  • Water line
  • Grading close to being done (CAD work to be done)
  • Design is completed including water and drainage, work will be submitted next week
  • We will engage our septic engineer after our first round of review
  • TIA is being worked on and close to being completed
2024-10-31
  • Civil Construction Plat will be submitted this week, with 30-45 days to review
  • During this revision period, they will refine the plat
  • Grading design has been done for drainage, main line is coming from the Northeast with another channel for runoff water coming from the North (middle of the property)

Disposition outlookPrepared in parallel — buyers take entitled and half-entitled projects

Projected exit · pro forma
Original projection · $4,148,000 net
Capital invested$2,384,000
×1.7projected *
Net disposition proceeds$4,148,000
Operation net result — a 74% project ROI$1,764,000
Line by line
Projected disposition price· sale of the entitled land, per the pro forma$5,400,000
Less selling costs· the gap between the registry's two figures — not itemised in the sources-$1,252,00023.2%
Net disposition proceeds$4,148,000
Less capital invested· project capitalization-$2,384,000
Operation net result$1,764,00074%

* Projected figures from the pro forma (original projection): they are neither a promise nor a guarantee of performance. The estimated disposition date is the expected acquisition date plus the hold period.

The deal as the registry holds it
LQWealth Track Record.xlsx · as of 2026-09-18
Projected resale price (net)
$5,400,000
Net sale price
$4,148,000
Projected net profit
$1,764,000
Investor ROI
48%
Investor IRR
16%
Project ROI
74%
Hold period
24 - 36 M
Sale timeline
Registry field; the pro forma window Q3 2026 – Q3 2027 governs
Q2 - Q4 2027 · differs

Source: LQWealth Track Record.xlsx › "Entitlements" · as of 2026-09-18 — disposition figures are often projected, to be validated

When — the sale timelines in the sources
The pro forma window governs

The estimated disposition date is the acquisition date plus the hold period; the LQWealth registry carries its own date and flags its disposition figures as projected, to be validated.

Surfaces that disagree
1 points for the team to reconcile
Sale timeline
Registry Q2 - Q4 2027 · pro forma window Q3 2026 – Q3 2027 (acquisition date plus the hold)
Pro forma governs

None of these changes the projected figures; each one is a field to align across the registry, the data room and the engineer's set so that every surface says the same thing.

What an investor getsPro forma, original projection — not a promise of performance

48%Projected investor ROI — total profit on invested capital, over a 24–36 month hold.16% target IRRPer $100,000 invested$100,000Capital back$48,000Projected profit$148,000Projected totalArithmetic on the pro forma ROI of 48%, shown per $100,000 to make the scale readable. Projected — neither a promise nor a guarantee of performance.
Investor
split
Share of profits after the preferred return$1,146,600net investor profit on top of the pref65%Of net result
Hold
period
Capital is committed until the entitled land sellsQ3 2026 – Q3 2027estimated disposition window24–36Months

Project plans — evolutionfrom concept to final plan

The layout plan sharpens as entitlements progress: each version below reflects county and engineering feedback — value creation in motion.

PDFSite plan
Loading the plan…

Finances — on the recordRaise · seller financing · taxes · pro forma summary · costs paid

Raise100%
Project capitalization$2,384,000
Total project budget$1,644,000

Budget = sum of pro forma line items — projected figures, to be validated

Seller financing

Free and clear — no seller financing, no debt.

Source: RiseQuire Portfolio Promissory Notes Information.xlsx · 2026-09-18

Property taxes

Parcels tracked1
Taxes paid (current cycle)1/1 · $12,007

Source: Tax Payment Information.xlsx · 2026-09-07

Pro forma (summary)

Total Acquisition Costs$1,159,000
Total Carry Cost$60,000
Land Planning Total$425,000

Source: RiseQuire Portfolio Pro Forma Overview.xlsx · 2026-09-10 — projected figures, to be validated

Pre-acquisition & entitlement costs

Engineering work for Entitlement · LJA Engineering$308,000
Taxes
Insurance
Total costs · paid $308,000$308,000

Source: Portfolio Expenses.xlsx · 2026-09-15

Ownership & proofEntity · GP · management · the official county record

Who holds the land

State registry = entity ownership (the LLC) · county site = land ownership — two distinct official proofs.

1 record
1 open today
Proof #2 — land ownership
County website — parcel record

Official county registry — Bexar County, TX.
APN : 04010-000-0116 — paste into the county search

Documents & materialsData room · webinar replay · brochure

Investment presentation2 documents
PDFBrochure
XLS
PDFBoundary Survey - Levé de délimitation (Jan 2023)2026-08-31
PDFT1 Title Commitment Complete Elmendorf TX 49 ac2026-08-21
PDFGeotechnical Engineering Report - Rapport d'étude géotechnique (Feb 2025)2026-08-13
PDFGeotechnical Engineering Services - Services d'ingénierie géotechnique (Jan 2025)2026-08-13
PDFTree Survey - Relevé arboricole (Sep 2024)2026-08-13
PDFSurvey Metes and Bounds - Levés de délimitation avec description juridique des limites (Jan 2023)2026-08-10
PDFBURTON ARCHEOLOGICAL SERVICES LLC - Invoice 2026-01 Mathis MH and RV Park arch survey2026-03-20
PDFTree survey entitlement process2025-04-08
PDFHoyt Seidensticker Invoice Septic Feasibility LQPF112025-04-08
PreviewPick a file — it reads here, in the page.
Nothing open yetPick a file in the middle column. PDFs render page by page; workbooks sheet by sheet.
Upcoming project documents
Each one joins the current documents once filed in the data room.
Preliminary layout & lot plan — revision 1Preliminary layout & lot plan — revision 2Preliminary layout & lot plan — revision 3Final layout plan — approved once entitlements are secured

QuestionsThe LandQuire team answers you directly on this page

Frequently asked
When will I receive my K-1?
Your K-1 is prepared annually following a draft → review → final version cycle, with a goal of sending it out before the end of March. You will be notified as soon as it is available.2026-08-15
When and how am I distributed after a sale?
After the sale of an asset, the distributions follow the structure outlined in the contract: return of the invested capital, then the preferred return, and finally the sharing of the capital gain (promote). The exact schedule and amounts are communicated to you at the time of each distribution.2026-08-15
Can I convert my stake into another portfolio?
It is possible under certain conditions: a conversion requires the signing of the corresponding documents. Our team will assist you on a case-by-case basis to validate eligibility and formalize the operation.2026-08-15
Why invest in the United States?
Investing in the USA offers many advantages, not least in the real estate sector, which remains very dynamic in high-growth states such as Texas and Nevada. This trend has accelerated since the post-COVID era, with companies, particularly in the technology sector, relocating from high-cost states such as California and New York to the Sunbelt region. This migration has stimulated job creation and dramatically increased demand for housing, making these regions particularly attractive to investors. Moreover, land prices in the United States appreciate naturally due to the depth of the market and the abundance of undeveloped land. By contrast, Europe faces land saturation and limited supply, making large-scale projects more difficult. The administrative process in the U.S. is also more efficient, with permit approvals quicker than in France, where major construction projects - particularly high-rise projects - often involve lengthy and costly bureaucratic hurdles. Real estate investments in the United States tend to offer higher returns, supported by a more favorable tax regime than in France. In high-growth states, the chronic housing shortage is driving up property values. Finally, investing in the United States offers currency diversification thanks to the strength and stability of the US dollar, while providing a secure legal framework that guarantees solid protection of property rights.2026-09-14
How do you select land for your projects?
We follow a rigorous methodology to select land for our projects, based on an in-depth analysis of over 120 criteria. This approach enables us to identify high-value opportunities while ensuring compliance with local planning and development policies. As a proptech company, we maximize the use of open landowner data, giving us exclusive access to off-market properties that often offer higher profitability. Our selection process begins with a large-scale analysis of all 3,216 U.S. counties, using key indicators such as 10-year population growth, number of properties sold and listed, and average time to resale. By analyzing data from sources such as Zillow and Redfin, we focus on around 100 counties where demand is strong, supply limited and properties sold quickly. Once we've identified the most promising counties, we gather property data and apply a thorough evaluation process, assessing over 100,000 parcels per month. Each parcel is rated on factors such as topography, accessibility, resistance to natural disasters, property status and profitability potential. Priority is given to A- and B-rated plots located in dynamic suburban areas with strong infrastructural connectivity. In addition, the land selected must meet our ESG objectives, minimizing environmental impact and guaranteeing easy development, with a preference for flat, lightly wooded land. We make strategic purchase offers based on the estimated value of the land, securing properties at below-market prices in order to guarantee high profit margins. For example, a parcel of land valued at $100,000 can be offered for $30,000 to $40,000. This approach guarantees strong value appreciation, further enhanced by our land improvement efforts, which transform raw parcels into highly attractive assets ready for development. Our evaluation process takes into account factors such as location, access to infrastructure, economic feasibility and environmental impact. We also work closely with local authorities to ensure that our projects fit in with urban development plans. By following this strategy, we respond effectively to strong market demand while offering substantial returns to our investors, in line with trends in high-growth markets.2026-09-14
Show 11 more
What kind of projects are you developing?
Our main focus is on developing residential land to meet the growing demand for housing. However, we have also undertaken hotel and commercial infrastructure projects when attractive opportunities arise.2026-09-14
Why do you concentrate on residential projects?
The residential market is experiencing structurally high demand, particularly following the demographic changes brought about by the pandemic. This constant demand ensures greater stability and lower risk than other segments, such as office space or warehouses, which are subject to greater fluctuations.2026-09-14
What environmental criteria do you take into account in your projects?
We select land with minimal impact on the environment, favoring plots that are lightly wooded and not prone to flooding. If trees have to be felled, we compensate by replanting and ensure that green spaces are integrated into our projects for the families who will live there.2026-09-14
Who carries out the urban planning analysis?
We work with LJA Engineering, a company that has contributed to the development of over 10,000 residential lots per year and has extensive experience in municipal approvals. Thanks to its close relationships with Texas planning authorities, LJA is able to anticipate regulatory constraints and structure projects accordingly. Their expertise helps us to determine the number of lots that can be authorized, which in turn allows us to optimize our projects before acquisition. By partnering with LJA, we significantly reduce the risk of unexpected permitting issues, allowing us to confidently move forward with well-planned developments.2026-09-14
What is the minimum investment required to become a partner?
The minimum investment to partner with us is generally between $50,000 and $100,000, depending on the project. These thresholds are set not only to ensure accessibility while maintaining high standards, but also because of regulatory requirements imposed by the US authorities. Unlike a traditional investment fund, our investors participate directly in specific projects, giving them greater transparency and control over the opportunities they choose to invest in.2026-09-14
Do you offer opportunities other than residential land projects?
Yes, although our main expertise is in residential land, we have also worked on specific projects such as hotels and data centers. We are constantly exploring new opportunities based on market needs.2026-09-14
What is the average duration of the projects you propose?
The average duration of our projects is between 18 and 24 months. This depends on the complexity of the project and its location, but we strive to provide realistic and optimal timescales to maximize return on investment.2026-09-14
What return can I expect from your projects?
Our projects offer competitive returns, often superior to those of other types of real estate investment. Although results vary according to the specific features of each project, our rigorous methodology guarantees attractive gains for our investors. The expected rate of return, or ROI (Global Return on Investment), is determined by taking into account all the key elements of the operation. This includes the land acquisition price, as well as engineering, development and site preparation costs. Once these steps have been completed, we legally define the number of lots that can be extracted from the land, in compliance with local regulations. The resale is then carried out at a unit price per lot based on an in-depth analysis of local market values. After deduction of transaction-related costs, such as closing and administrative fees, net profit is calculated. This net return, shared with our investors, offers the prospect of significant profitability while covering the costs inherent in the operation. Our structured approach allows us to optimize the value of each project while guaranteeing attractive margins for our financial partners.2026-09-14
What are the risks associated with this type of investment?
As with any investment, there are inherent risks. However, we mitigate them by rigorously selecting land, working with local experts and carrying out a thorough analysis of opportunities before committing to a project. With our approach, you invest in land development projects aimed at transforming raw land into lots ready for sale. This process includes land acquisition, engineering studies and the legal definition of lots for resale at competitive unit prices. This model guarantees transparency and a tangible investment backed by real assets for each project. The US real estate market, particularly in states like Florida and Texas, is characterized by high demand. Our development projects meet this growing need, but like any market, certain risks can arise: 1. Risk of delayed or reduced sales Although we anticipate competitive prices, it is possible that some lots may be sold at lower prices in the event of an economic slowdown or a drop in local demand. However, such adjustments are rare and generally have no impact on overall operations. 2. Fluctuations in infrastructure costs Development costs can sometimes exceed initial estimates. To remedy this, we build in safety margins to absorb these variations. 3. Changes to local regulations Changes in zoning legislation or updates to local policies can have an impact on timescales or costs. We minimize this risk through early collaboration with municipalities, validating the feasibility of our projects in advance. With over 140 completed projects, we acquire land with a pre-established value, ensuring that it can be resold at market price, even in the event of an adjustment. Risk mitigation measures Project-specific limited liability companies: Each project is structured as a separate limited liability company, allowing risks to be isolated. If one project runs into difficulties, this does not affect the others, guaranteeing investment security. Long-term tangibility of assets: Investors hold shares in a company dedicated to each specific project. If, at the end of the contractual period (around four years), certain lots remain unsold, we offer investors the possibility of direct ownership of these lots, providing long-term security. A transparent, tangible model By investing with us, you become a shareholder in a company dedicated to land acquisition and development. Our pre-development operations aim to maximize the value of land by making it ready for construction with the necessary infrastructure and legally defined lots in compliance with local regulations. This tangible asset, held through your shares, ensures that your investment is linked to a real, physical property. Commitment to investors Our priority is to build long-term relationships with our investors by offering flexible solutions and maximizing profitability while minimizing risk. Thanks to our expertise and strong local presence, we proactively manage potential challenges to ensure the success of every project.2026-09-14
Can investors from any country invest with LandQuire?
LandQuire works with investors from many countries around the world. However, investor eligibility is subject to applicable U.S. laws and regulations, including economic and trade sanctions administered by the Office of Foreign Assets Control (OFAC) of the U.S. Department of the Treasury, as well as applicable KYC and AML requirements. LandQuire does not accept investments from individuals, entities, or jurisdictions where such investments would be prohibited or restricted under applicable sanctions laws or regulations. In addition, certain jurisdictions may be excluded under LandQuire’s internal compliance and risk management policies. All potential investors undergo a compliance review, and final eligibility is determined during the onboarding process.2026-09-14
Do you offer investors any guarantees?
We guarantee total transparency in our processes and clear, detailed contracts designed to protect the interests of our investors. Here are the key elements that ensure the security and reliability of our projects: 1. Land ownership LandQuire owns the land for each project. By investing, investors obtain tangible security in the form of shares in a company that owns a real estate asset. 2. Property insurance All acquired land is insured, providing additional protection against unforeseen events. 3. Proven track record Our history demonstrates our ability to manage projects efficiently and generate attractive returns for investors. 4. Preferred shares for investors Investors receive preferred shares, which give them priority rights to profits and distributions. 5. Exclusive allocation of funds Our contracts guarantee that the funds raised are used exclusively for the specific project, eliminating the risk of dilution or unforeseen reallocation. 6. Market dynamics Although this is not a formal guarantee, we operate in strategic markets such as Florida, where strong demand for land and housing is driving the appreciation of our assets. These measures do not replace a full guarantee, but considerably reinforce the solidity of our projects. They offer investors a high level of security based on tangible assets, rigorous processes and strategic positioning in attractive markets.2026-09-14

TraceabilityEvery field, its source and its date

FieldValueSourceAs ofConfidence
Stage / statusUnder MgmtLQWealth Track Record.xlsx › "Entitlements"2026-09-18LQWealth registry (Track Record)
Acquisition date2024-07-22Closing statement (data room)Décompte de clôture (data room)
LocationElmendorf, TXLQWealth Track Record.xlsx › "Entitlements"2026-09-18LQWealth registry (Track Record)
Data room documentsfolder updated 2026-08-28SharePoint (Shared)2026-08-28Files

Source: LQWealth registry + Willem files · automatically refreshed from LandQuire internal files and tools, several times a day · read-only.