PF19 · Greenville, Texas

Developer project sheet

All projects
LandQuire desk
PF19Build to Rent · MHP · RVComing

Greenville, Texas

60.44 acres · 354 lots projected · Mobile Home / RV Park

29%
Entitlement 29% completeStage: Plan production · as of September 15, 2026

Coming — entitlement is under way; the land is not on the market yet.

Asking price · indicative$4,926,600
Price per lot$13,917
Price per acre$81,512
Build-ready (target)March 2027

Asking price is indicative.

1The landsatellite & boundaries · parcel · location · photos · 3D terrain

3D terrain
Click two points to measure · layers top right
✓ LandQuire owned
Under Mgmt
✓ LandQuire owned
Under Mgmt
Satellite + boundaries · parcel in yellow · measure the distance to sewer, road or schoolEsri, Maxar, USDA · OpenStreetMap

60.44 acres · Greenville, Texas · 354 lots projected · Mobile Home / RV Park

Project progressInstaGantt · 2026-09-23
29%Overall project progressrefreshed every 3 h
19Total tasks3Completed16Remaining
29%Plans and Reportsrefreshed every 3 h
5Total tasks0Completed5Remaining
Current milestoneSite development PlansEst. timeframe: November 2026Milestone progress25%
60%Fire Marshal Reviewrefreshed every 3 h
1Total tasks0Completed1Remaining
Current milestoneConstruction DocumentsEst. timeframe: October 2026Milestone progress60%
12%Site Development Permitrefreshed every 3 h
4Total tasks0Completed4Remaining
Current milestoneConstruction DocumentEst. timeframe: October 2026Milestone progress15%

Progress, task counts and target dates come from the team’s InstaGantt export, picked up automatically every 3 hours. Dates are planning targets, not commitments.

2Entitlement & timelinewhere each permit stands, and what comes next

Permit tracking — all 23 lines
29% complete
Current reviewSite development Plans25% · target November 2026
Lines233 complete · 20 upcoming
Next targetsSeptember 2026 · October 2026
Permit tracking — line by line, on the calendar
Hover a bar for start, duration and target
Task · start · duration%
FebMarAprMayJunJulAugSepOctNovDecJanFebMarApr
Target
Greenville MH ParkFebruary 2026 · 1 year 2 months 3 days
29%
March 2027
County MeetingFebruary 2026 · 1 day
100%
February 2026
SurveyingMay 2026 · 19 days
100%
May 2026
Conceptual PlanMay 2026 · 12 days
100%
June 2026
Plans and ReportsJune 2026 · 5 months 23 days
29%
November 2026
Site development PlansJune 2026 · 5 months 23 days
25%
November 2026
Storm Water Management PlansJune 2026 · 5 months 2 days
20%
November 2026
Traffic Impact AnalysisJuly 2026 · 2 months 22 days
15%
September 2026
Detension Pond Design and PlansJuly 2026 · 3 months 23 days
70%
November 2026
Public Street Improvement PlansAugust 2026 · 3 months 27 days
15%
November 2026
TxDot Driveway PermitJuly 2026 · 5 months 28 days
10%
December 2026
GEUS (Electric Provider)July 2026 · 4 months 25 days
25%
November 2026
Fire Marshal ReviewAugust 2026 · 2 months 22 days
60%
October 2026
Construction DocumentsAugust 2026 · 2 months 22 days
60%
October 2026
Hunt County (Reviews)August 2026 · 4 months 11 days
60%
December 2026
Site Development PermitAugust 2026 · 4 months 11 days
12%
December 2026
Construction DocumentAugust 2026 · 2 months 22 days
15%
October 2026
Storm WaterSeptember 2026 · 2 months 23 days
10%
December 2026
Sanitary Sewer Package PlantSeptember 2026 · 2 months 3 days
10%
November 2026
TrafficSeptember 2026 · 1 month 24 days
15%
November 2026
Shady Grove SUDAugust 2026 · 2 months 22 days
75%
October 2026
TCEQ Package Plant ApprovalAugust 2026 · 7 months 5 days
20%
March 2027
Project ApprovalDecember 2026 · 3 months 21 days
5%
March 2027

export 2026-09-23 · InstaGantt

Up next — from the project schedule
Plans and Reports
Traffic Impact Analysis
→ September 2026
Detension Pond Design and Plans
→ November 2026
Site development Plans
→ November 2026
Storm Water Management Plans
→ November 2026
Public Street Improvement Plans
→ November 2026
Fire Marshal Review
Construction Documents
→ October 2026
Site Development Permit
Construction Document
→ October 2026
Traffic
→ November 2026
Sanitary Sewer Package Plant
→ November 2026
Storm Water
→ December 2026
Unphased
Shady Grove SUD
→ October 2026
GEUS (Electric Provider)
→ November 2026
Hunt County (Reviews)
→ December 2026
TxDot Driveway Permit
→ December 2026
TCEQ Package Plant Approval
→ March 2027

3Site planfrom concept to final plan

The site plan as it stands today, with every earlier version — each one reflects county and engineering feedback.

PDFLatest plan
Loading the plan…

4Land & titlethe entity, the parcels and the official county record

Who holds the land
Parcels · 3
0473-0040-0000-400089-0010-0000-400089-0010-0010-40

The land is held by a project-dedicated LLC: state registry = entity ownership · county site = land ownership.

1 record
1 open today
Official record
County website — parcel record

Official county registry — Hunt County, TX. Paste the parcel number into the county search.

APN
0473-0040-0000-40 + 2 in the list

5Inquirewrite to us directly

LandQuirereadyland@landquire.com

Tell us your product, the number of lots and your timing.

Register interest