PF12 · Elmendorf, Texas

Developer project sheet

All projects
LandQuire desk
PF12Build to Sell · MHP · RVComing

Elmendorf, Texas

97 acres · 800 lots projected · Mobile Home / RV Park with Commercial

Plat & permit reviewStage as of September 15, 2026

Coming — entitlement is under way; the land is not on the market yet.

Asking price · indicative$9,235,000
Price per lot$11,544
Price per acre$95,206
Build-ready (target)December 2026

Asking price is indicative.

1The landsatellite & boundaries · parcel · location · photos · 3D terrain

3D terrain
Click two points to measure · layers top right
✓ LandQuire owned
LQ INVESTMENTS PORTFOLIO TWELVE LLC
✓ LandQuire owned
LQ INVESTMENTS PORTFOLIO TWELVE LLC
Satellite + boundaries · parcel in yellow · measure the distance to sewer, road or schoolEsri, Maxar, USDA · OpenStreetMap

97 acres · Elmendorf, Texas · 800 lots projected · Mobile Home / RV Park with Commercial

Project progressInstaGantt · 2026-09-23
100%Surveyingrefreshed every 3 h
4Total tasks4Completed0Remaining
100%SAWSrefreshed every 3 h
5Total tasks5Completed0Remaining
92%Bexar Countyrefreshed every 3 h
6Total tasks5Completed1Remaining
Current milestoneTCEQ approval for WWTF permitEst. timeframe: December 2026Milestone progress75%
100%COSA Technical Reviewsrefreshed every 3 h
10Total tasks10Completed0Remaining
95%Letters of Certificationrefreshed every 3 h
5Total tasks3Completed2Remaining
Current milestoneSAWSEst. timeframe: October 2026Milestone progress90%

Progress, task counts and target dates come from the team’s InstaGantt export, picked up automatically every 3 hours. Dates are planning targets, not commitments.

2Entitlement & timelinewhere each permit stands, and what comes next

Permit tracking — line by line, on the calendar
Hover a bar for start, duration and target
Task · start · duration%
Q32024Q42024Q12025Q22025Q32025Q42025Q12026Q22026Q32026Q42026
Target
Matthis MH/RV Park with CommercialSeptember 2024 · 6 months 11 days
100%
March 2025
SurveyingSeptember 2024 · 3 months 5 days
100%
December 2024
BoundarySeptember 2024 · 19 days
100%
October 2024
TreeSeptember 2024 · 1 month 3 days
100%
October 2024
Subdivision PlatOctober 2024 · 2 months
100%
December 2024
TopographicSeptember 2024 · 19 days
100%
October 2024
Conceptual PlanOctober 2024 · 12 days
100%
October 2024
Country MeetingOctober 2024 · 3 months 2 days
100%
January 2025
COSA MeetingOctober 2024 · 3 months 2 days
100%
January 2025
Plans and ReportsOctober 2024 · 8 months 24 days
100%
July 2025
Site Development PlansOctober 2024 · 8 months 24 days
100%
July 2025
Traffic Impact AnalysisOctober 2024 · 5 months 9 days
100%
March 2025
Storm Water ManagementNovember 2024 · 8 months 10 days
100%
July 2025
Public Water Main ImprovementNovember 2024 · 8 months 10 days
100%
July 2025
Detention Pond DesignNovember 2024 · 4 months 25 days
100%
March 2025
Tree Mitigation PlanOctober 2024 · 8 months 24 days
100%
July 2025
SWPPPNovember 2024 · 8 months 10 days
100%
July 2025
SABuild Development ServiceNovember 2024 · 2 years 2 months
94%
December 2026
SAWSJanuary 2025 · 1 year 2 months 29 days
100%
March 2026
USAJanuary 2025 · 1 year 2 months 29 days
100%
March 2026
Water QualityJanuary 2025 · 1 year 2 days
100%
December 2025
SewerJanuary 2025 · 1 year 2 days
100%
December 2025
WaterJanuary 2025 · 1 year 2 days
100%
December 2025
AquiferJanuary 2025 · 1 year 2 days
100%
December 2025
Bexar CountyFebruary 2025 · 1 year 11 months 1 day
92%
December 2026
TrafficFebruary 2025 · 8 months 1 day
100%
October 2025
General PlattingFebruary 2025 · 8 months 1 day
100%
October 2025
TCEQ approval for WWTF permitFebruary 2025 · 1 year 11 months 1 day
75%
December 2026
Storm DrainFebruary 2025 · 10 months 2 days
100%
December 2025
Flood PlainFebruary 2025 · 10 months 2 days
100%
December 2025
Driveway PermitFebruary 2025 · 1 year 4 months 15 days
100%
June 2026
COSA Technical ReviewsDecember 2024 · 10 months 2 days
100%
October 2025
Office of Historic PresDecember 2024 · 10 months 2 days
100%
October 2025
Parks and RecreationDecember 2024 · 10 months 2 days
100%
October 2025
AddressingDecember 2024 · 10 months 2 days
100%
October 2025
SubdivisionDecember 2024 · 10 months 2 days
100%
October 2025
Habitat CompletenessDecember 2024 · 10 months 2 days
100%
October 2025
TCI - Storm WaterDecember 2024 · 10 months 2 days
100%
October 2025
Engineering TIADecember 2024 · 10 months 2 days
100%
October 2025
Engineering TreesDecember 2024 · 10 months 2 days
100%
October 2025
CPS ROWDecember 2024 · 9 months 4 days
100%
September 2025
TCI - TIADecember 2024 · 6 months 24 days
100%
July 2025
Letters of CertificationNovember 2024 · 1 year 11 months 29 days
95%
October 2026
SAWSFebruary 2025 · 1 year 8 months 20 days
90%
October 2026
Bexar CountyMarch 2025 · 1 year 7 months 20 days
85%
October 2026
Office of Historic PresNovember 2024 · 1 year 8 months 11 days
100%
July 2026
Parks and RecreationNovember 2024 · 1 year 8 months 21 days
100%
July 2026
DSDMay 2025 · 1 year 2 months 22 days
100%
July 2026
Plat RecordationJune 2025 · 1 year 7 months
60%
December 2026

export 2026-09-23 · InstaGantt

Up next — from the project schedule
Bexar County
TCEQ approval for WWTF permit
→ December 2026
Letters of Certification
SAWS
→ October 2026
Bexar County
→ October 2026
Unphased
Plat Recordation
→ December 2026

3Site planfrom concept to final plan

The site plan as it stands today, with every earlier version — each one reflects county and engineering feedback.

PDFConceptual plan
Loading the plan…

4Land & titlethe entity, the parcels and the official county record

Who holds the land
Parcels · 1
04125-000-0011

The land is held by a project-dedicated LLC: state registry = entity ownership · county site = land ownership.

1 record
1 open today
Official record
County website — parcel record

Official county registry — Bexar County, TX. Paste the parcel number into the county search.

APN
04125-000-0011

5Inquirewrite to us directly

LandQuirereadyland@landquire.com

Tell us your product, the number of lots and your timing.

Register interest